TIMELINE:

Week of February 15

  • Feb 15: Finish choosing PCR Type

  • Feb 17: Continue research on chosen PCR Type

  • Feb 18: (Finish?) research on PCR Type, begin designing DNA

Week of February 22 - NINTH WEEK

  • Feb 22: begin work on poster this week (?), do any further research from last week

  • Feb 24:

  • Feb 25:

Week of February 29

  • Feb 29: Finish designing DNA, begin working on control for assay (Lab work/research)

  • March 2: Continue working on control for assay (Lab work)

  • March 3: Finish control for assay work, begin tinkering with protocols (Lab work/research)

Week of March 7

  • March 7: Continue tinkering with protocols, begin assay testing

  • March 9: Continue testing assay, tinkering with protocols

  • March 10: Continue testing assay, tinkering with protocols

Week of March 14

  • March 14: Finish all lab work, finish poster

  • March 16: Close any loose ends

  • March 17: Complete all goals (see below and flowchart)

  • perform PCR on methylated DNA and detect the methylation patterns; Will the DNA remain methylated after PCR?

  • have done electrophoresis to prove DNA is methylated